Route 96 bridge over Turnback Creek west of Halltown to be closed


(From MODOT)

Route 96 Bridge Over Turnback Creek to CLOSE Week of July 18 for Rehabilitation

Contractor crews are set to CLOSE the Missouri Route 96 bridge over Turnback Creek west of Halltown for up to 115 days beginning the week of July 18 to rehabilitate the bridge, the Missouri Department of Transportation said.

Crews will demolish the existing bridge deck/driving surface and beams, leaving the piers and foundation in place to be re-used in the new structure. In addition, the contractor will add new barrier walls, guardrail at the ends of the bridge, an upgraded drainage system and new permanent striping.








The bridge also will be widened by three feet to a total of 30 feet to accommodate two 12-foot-wide lanes with three-foot wide shoulders.

This bridge was built in 1960 and is in a deteriorating condition. Approximately 6,200 vehicles cross the bridge daily.

Traffic Impacts

All lanes of Route 96 will be CLOSED over Turnback Creek for up to 115 days

Drivers will have access to driveways and entrances on either end of the bridge, but will not be able to drive through the work zone

Drivers will be directed along a signed detour using I-44 and I-49

Signs and message boards will alert drivers approaching the work zone






Drivers should consider alternate routes during the project

Check MoDOT’s Traveler Information Map for road closings/traffic impacts

Weather and/or construction delays could alter the work schedule.

This work is part of a three-year project to improve 25 bridges within 15 miles of I-44 across the Southwest District. Of the 25 bridges in the project, known as the I-44 Corridor Bridge Bundle, seven (7) are mainline I-44 bridges, five (5) are I-44 overpass bridges and the remaining bridges are on adjacent routes over various features. Sixteen (16) bridges will be replaced and nine (9) bridges will receive major rehabilitation work.

All work in 2022 will be in Lawrence County, where crews will replace five (5) bridges and rehabilitate four (4) others.

More information about this project can be found on the project website – I-44 Corridor Bridge Bundle.

Project Details

Prime Contractor – The ESS TeamEmery Sapp & Sons, Inc. – Columbia
Parsons Transportation Group, Inc. – St. Louis
Total Project Cost: $43.2 million
Contract Completion Date: September 30, 2024

The ESS Team is a partnership of engineering and construction firms that will design and construct the project with oversight by MoDOT and the Federal Highway Administration.