(From MODOT)
Update for Week of March 30: Route 160 Widening Willard to Springfield
TRAFFIC STOPS of up to 15 minutes on Route 160 for blasting one time per day between 10 a.m. and 2 p.m. Monday-Friday
TRAFFIC SHIFT on Route 160 at Hunt Road for construction of pedestrian underpass
Work Scheduled:
-Blasting and moving rock in areas between Farm Road 115 and Farm Road 123
-Grading and laying rock for new highway lanes on south end of project near I-44
-Installing drain pipes in various locations
All the work is highly dependent on the weather
Traffic Impacts:
TRAFFIC SHIFT on Route 160 at Hunt Road:
-Traffic shifted to the west
-Northbound-to-westbound turn lane shortened
-Crews and equipment close to traffic on east side of Route 160
TRAFFIC STOPS for rock blasting:
-Route 160 traffic stopped for up to 15 minutes once a day at some point between 10 a.m. and 2 p.m. Monday-Friday
-Traffic also may be stopped on nearby county farm roads
-Flaggers will stop traffic
-Rock blasting could take several months to complete
-Equipment crossing county farm roads at times. Short-term traffic stops by flaggers to allow equipment to cross the road.
-Route 160 shoulder closed in areas at times
-Crews and equipment close to traffic
-Equipment entering and leaving work areas
-Crews may work Saturdays and Sundays to make up work missed due to weather/construction delays
(Weather or construction delays could alter the work schedule.)
Project Summary:
Widen Route 160 to four lanes between I-44 in Springfield and Jackson Street in Willard
Resurface the existing lanes of Route 160 between I-44 in Springfield and Route AB in Willard
Install concrete traffic barrier between lanes in areas
Add a pedestrian underpass underneath Route 160 at Hunt Road
Add a new box culvert to carry Frisco Highline Trail underneath Route 160 at Trail Mile 3
Add street lighting at intersections
Intersection improvements:
J-turn at Farm Road 123/Westgate Avenue
Right-in/Right-out at Haseltine Road (Farm Road 115)
Roundabout at Farm Road 94 near quarry
Add left-turn lane at Hughes Road
Roundabout at Farm Road 103/Melville Road/Hunt Road
Roundabout at Jackson Street
Add turn lanes at Greene County Route AB
Prime Contractor: APAC-Central, Springfield
Completion Date: December 1, 2020
Total Project Cost: $18.6 million