(From MODOT)TRAFFIC ALERT: New Traffic Pattern Coming to I-44 Near Mile Marker 41 Beginning Week of April 24
What: Traffic will remain one lane in each direction, but will shift to outside lanes while crews replace bridges over Freistatt Branch
When: Beginning week of April 24 and remaining in this pattern until completion of the project, sometime in mid- to late June
Traffic Impacts
I-44 will be reduced to one lane of traffic in each direction west of Mt. Vernon near Mile Marker 41 until completion of the project, sometime in mid- to late June
Drivers should expect slowed traffic, traffic delays
Crews and large equipment near traffic
Speed limit will be reduced to 60 mph through work zone
Signs and message boards will alert drivers approaching the work zone
Drivers should consider alternate routes during the project
Check MoDOT’s Traveler Information Map for road closings/traffic impacts
Weather and/or construction delays could alter the work schedule.
This work is part of a three-year project to improve 25 bridges within 15 miles of I-44 across the Southwest District. Of the 25 bridges in the project, known as the I-44 Corridor Bridge Bundle, seven (7) are mainline I-44 bridges, five (5) are I-44 overpass bridges and the remaining bridges are on adjacent routes over various features. Sixteen (16) bridges will be replaced and nine (9) bridges will receive major rehabilitation work.
More information about this project can be found on the project website here: I-44 Corridor Bridge Bundle Design-Build Project | Missouri Department of Transportation (modot.org)
Project Details
Prime Contractor – The ESS TeamEmery Sapp & Sons, Inc. – Columbia
Parsons Transportation Group, Inc. – St. Louis
Total Project Cost: $43.2 million
Contract Completion Date: September 30, 2024
The ESS Team is a partnership of engineering and construction firms that will design and construct the project with oversight by MoDOT and the Federal Highway Administration.
Parsons Transportation Group, Inc. – St. Louis
Total Project Cost: $43.2 million
Contract Completion Date: September 30, 2024
The ESS Team is a partnership of engineering and construction firms that will design and construct the project with oversight by MoDOT and the Federal Highway Administration.
|
No comments:
Post a Comment